How long does a remodel take?
By All Purpose Anytime Services LLC
Less time on site than most people expect, more time overall. Permits, inspections, material lead times and homeowner decisions stretch a project, and only one of those is up to the contractor.
Where the time goes
Demolition is fast. Framing is fast. Drywall is not fast, because finishing needs coats and coats need to dry, and rushing that is how you get seams that show a year later. Tile needs setting time before grout. Paint needs the surface to be ready before it is worth putting on.
Between those there are inspections. Rough inspections have to pass before anything gets closed up, and an inspector who cannot come until Thursday stops the job until Thursday regardless of who is standing there.
The two things that stretch a job most
Selections not made. A kitchen cannot be finished around a cabinet decision that has not happened, and a tile that gets chosen in week three is a tile that arrives in week six. Every day a decision sits open is usually a day added to the end.
Long lead items ordered late. Cabinets, windows, custom doors and some appliances have lead times measured in weeks or months. Ordering those at the start, before demolition, is the single biggest thing that keeps a project on schedule.
What a real schedule looks like
A schedule should be built backwards from a completion date, with the trades in sequence and the long lead items ordered at the front. It should name the points where you have to decide something, with a date attached.
We do not publish typical durations by project type, because a bathroom in a slab ranch and a bathroom on the third floor of a rowhouse with a shared wall are not the same project. You get a schedule for your job with the sequence in it.
How long does a kitchen remodel take?
Plan on several weeks with the kitchen out of use, and longer from the day you sign, because the cabinets are ordered before demolition and the maker sets how long they take to arrive. A permit adds its review time before the start.
On site the order is demolition, rough plumbing and electrical with their inspections, drywall, flooring, then cabinets. Then comes a pause: the countertop can only be templated once the cabinets are in, and then it has to be made. The backsplash goes on last. Your written schedule shows the countertop pause so you can set up a temporary kitchen for it. More on the steps is on our kitchen remodeling page.
How long does a home addition take?
Months, and the approvals before anyone breaks ground take a real share of them. Design, engineering and the permit come first, and in a DC historic district the Historic Preservation Review Board reviews the addition before the Department of Buildings issues a permit.
Then the build runs foundation, framing and roof, closing in, opening the old wall to join the house, the trades with their inspections, and the finishes. We give you the approvals part of the timeline separately, so it is visible from day one. The addition cost guide covers what moves the price.
Living in it while it happens
For a single room, containment and daily cleanup make it liveable. For a kitchen, plan for the stretch with no kitchen and set up somewhere to cook before demolition rather than during it.
On occupied work we phase the noisy scopes and keep a path through the house. Commercial jobs get the same treatment, run after hours where the business has to keep trading.